I just started using DotProject and this might be a stupid question...but I couldn't find it anywhere:-(

Problem:
When assigning human resources (team memebers) to a task I should be able to verify the availability of the resource first.

Is there a way to verify the availability of the resource first while I'm in the process off assigning tasks?
This seems a key feature of a PM application, so I assume it's going to be implemented in DotProject....but I just can't find it.

Thanks for your help!!!

Carsten

ajdonnison
03-06-05, 08:16 PM
Full resource management such as you suggest requires user-level calendars along with project calendars. These are slated for the v.3 release.

vncoder
03-06-05, 08:19 PM
This is not available in the current version.
It is planned for version 3.

carsten
03-06-05, 08:32 PM
OK...thanks for your answer.

Is there any indication as of when v3 will be released? I know you can't give me a date....but are we talking about weeks, months, years?

Thanks,
Carsten