I'm using Mac 10.3.9, php4.3.11, Apache 1.3 & MySQL 4.024. When I have a dynamic task pulling dates from the child tasks, the dates adjust accordingly but the Duration calculation comes up with a strange number (see below). Why 15.33 days? I can't figure out where that number is coming from.

Task Name Start Date Duration Finish Date
RBC Materials 05/09/2005 15.33 days 06/29/2005 (dynamic task)
DSC Scanning 05/09/2005 20 days 06/03/2005
Image QR 06/06/2005 8 days 06/15/2005
OCR & Chunking 06/16/2005 10 days 06/29/2005
Derivatives 06/16/2005 8 days 06/27/2005

Thanks,