jhonwilliams
04-10-11, 08:38 AM
Hi,
I have a little problem with the dotProject task, I need register the task with 0.5 hour o 1.5 hour, but when save the task the hour is truncate and delete the real value. Example
0.5 hours in the database is 0.0
1.5 hours in the database is 1.0
Try modify the record in the database and is great, but when the dotproject edit/update the task, the again truncate the time data.
Thanks
I have a little problem with the dotProject task, I need register the task with 0.5 hour o 1.5 hour, but when save the task the hour is truncate and delete the real value. Example
0.5 hours in the database is 0.0
1.5 hours in the database is 1.0
Try modify the record in the database and is great, but when the dotproject edit/update the task, the again truncate the time data.
Thanks